The control of environmental conditions such as relative humidity and temperature is paramount in industrial buildings. Our experience, with exactly the right products, solutions and services, help our industrial customers to enhance their productivity, efficiency and to operate more flexibly.
Frontier Oil Refinery (El Dorado KS and Cheyenne, WY)
Frontier Oil Refinery (El Dorado KS and Cheyenne, WY)
Firelake was the control contractor of choice for multiple Frontier Oil locations including Cheyenne, Wyoming and El Dorado, Kansas. These design build projects were for critical sites such as labs, storage facilities, and testing facilities. Building Automation is critical to the operation and the safety of the business.
Water Treatment Plants
Water Treatment Plants
Projects include Cedar Creek Waste Water, Fishing River Waste Water, and various pumping stations throughout the Midwest. Firelake executes these projects by designing, managing, procuring material, installing, and commissioning the HVAC and ventilation systems. Firelake adds value to these projects because of our experience in dealing with the specialized requirements such as explosion proof material.
Diamond Pet Foods (MO, AR, CA, SC)
Diamond Pet Foods (MO, AR, CA, SC)
Diamond Pet Foods had an initiative to increase the comfort and air quality in their manufacturing areas. Firelake installed a Johnson Controls Facility Explorer system in multiple locations across the U.S. including California, Arkansas, South Carolina, and Missouri. These systems were all connected back to a central server for monitoring and control in one location. Equipment on these projects include custom make-up air units used to provide fresh air to the processing plant. The make-up air units were installed and programmed to provide fresh air and comfort to the space. With limited staff, Diamond Pet Foods can now manage facilities all across the U.S. from one location.
Frontier Oil Refinery (El Dorado KS and Cheyenne, WY)
Firelake was the control contractor of choice for multiple Frontier Oil locations including Cheyenne, Wyoming and El Dorado, Kansas. These design build projects were for critical sites such as labs, storage facilities, and testing facilities. Building Automation is critical to the operation and the safety of the business.
Water Treatment Plants
Projects include Cedar Creek Waste Water, Fishing River Waste Water, and various pumping stations throughout the Midwest. Firelake executes these projects by designing, managing, procuring material, installing, and commissioning the HVAC and ventilation systems. Firelake adds value to these projects because of our experience in dealing with the specialized requirements such as explosion proof material.
Diamond Pet Foods (MO, AR, CA, SC)
Diamond Pet Foods had an initiative to increase the comfort and air quality in their manufacturing areas. Firelake installed a Johnson Controls Facility Explorer system in multiple locations across the U.S. including California, Arkansas, South Carolina, and Missouri. These systems were all connected back to a central server for monitoring and control in one location. Equipment on these projects include custom make-up air units used to provide fresh air to the processing plant. The make-up air units were installed and programmed to provide fresh air and comfort to the space. With limited staff, Diamond Pet Foods can now manage facilities all across the U.S. from one location.
Hallmark Cards Manufacturing Plant (KS)
Hallmark Cards Manufacturing Plant (KS)
Firelake installed a complete Honeywell Building Automation system to control the HVAC at the Hallmark Manufacturing facility in Lawrence, Kansas. This project consisted of a large central plant and multiple air handlers that served the process areas and offices. Firelake is still working with Hallmark today on maintenance and further upgrades.
Ford Manufacturing Plant (MO)
Ford Manufacturing Plant (MO)
Ford Motors mandated that all of their facilities be controlled by the Tridium Niagara framework. When this project came out, Firelake was preferred to perform the work due to our knowledge of, and experience with, Tridium Niagara. The project involved integrating several pieces of equipment to a Niagara system. This project was unique because Ford has set guidelines for naming, graphics, programming etc. Firelake successfully met Fords needs and standards.
FedEx
FedEx
Firelake was contracted to design and perform the interlock wiring for the FedEx Hub located in Kansas City, Missouri. This project mainly consisted of high voltage interlock wiring to control ventilation and exhaust air. Firelake was brought in to design and oversee this process because of the complicated nature of the wiring configurations and relay logic.
Hallmark Cards Manufacturing Plant (KS)
Firelake installed a complete Honeywell Building Automation system to control the HVAC at the Hallmark Manufacturing facility in Lawrence, Kansas. This project consisted of a large central plant and multiple air handlers that served the process areas and offices. Firelake is still working with Hallmark today on maintenance and further upgrades.
Ford Manufacturing Plant (MO)
Ford Motors mandated that all of their facilities be controlled by the Tridium Niagara framework. When this project came out, Firelake was preferred to perform the work due to our knowledge of, and experience with, Tridium Niagara. The project involved integrating several pieces of equipment to a Niagara system. This project was unique because Ford has set guidelines for naming, graphics, programming etc. Firelake successfully met Fords needs and standards.
FedEx
Firelake was contracted to design and perform the interlock wiring for the FedEx Hub located in Kansas City, Missouri. This project mainly consisted of high voltage interlock wiring to control ventilation and exhaust air. Firelake was brought in to design and oversee this process because of the complicated nature of the wiring configurations and relay logic.